Blatnik Bridge Undergoing Repairs Beginning Monday

By KBJR News 1

Blatnik Bridge Undergoing Repairs Beginning Monday

May 8, 2012 Updated May 8, 2012 at 11:27 AM CST

Duluth, MN (Northland's NewsCenter) -- The Blatnik Bridge's northbound I-535 lanes will close on Monday, May 14 and will remain closed until mid-summer.

The Highway 2 Bong Bridge may be used as an alternate northbound route.

The I-535 southbound lane will remain open; yet, motorists may experience short, single-lane closures.

Motorists are asked to use caution and abide to posted speeds when crews work in the closed lanes.

After the northbound lane reconstruction, the southbound lanes on the I-535 Blatnik Bridge will be closed to traffic until October 2012.

The northbound lanes will be open at this time.

The Blatnik Bridge rehabilitation project consists of a major, two-year project. The project includes work that will extend the life of the bridge.

The following work is planned:

- To repair and strengthen gusset plates on the bridge's main span in order to improve the load-carrying capacity of the bridge.

- To sandblast and paint the main span from 10 feet above the deck and below. This will be done in order to protect the steel from corrosion.

- To replace the concrete traffic rail on the main span with a thinner, lighter weight rail. This will reduce the overall weight on the bridge which will increase the load carrying capacity.

- To replace the bridge deck expansion joints.

- To remove decorative outline lighting. The current lighting system will be removed so that areas of the bridge can be painted.

For more on this story, click here!

For more on the Blatnik Bridge Rehabilitation Project, click here!